Ozango Minerais S.A (Ozango) completed the early works activities programme at the Longonjo Rare Earth Refinery Project Site in H2 2024. The early works programme entailed construction and development of the mine infrastructure as well as the 107 person accommodation camp, the rehabilitation of the main access road to Project site, contractors laydown area and the progression of the Resettlement Action Plan (RAP) .
The Longonjo Rare Earth Refinery Project main construction activities commenced in May 2025 with key procurement and engineering contracts being placed and the resources assigned by the various service providers. The project delivery is being undertaken using the Owners Team Model with Engineering Service Provision by Lycopodium Africa (previously known as ADP Holdings Pty) who specialise in modular construction with extensive experience in Angola, and ProProcess Modular (Pty) Ltd (PPM) which has expertise in delivering modular process units across Africa.
The main earthworks and civil contractor, Grupo Nov, has expanded its workforce and additional earth-moving equipment to complete the terrace for the process plant, the contractor’s laydown area and to commence with the Tailings Storage Facility (TSF) earthworks construction.
The EWP electrical contractor, Elektra, have been re-engaged to complete the outstanding infrastructure and accommodation camp electrical works with Franteba engaged to finalise the temporary power supply for the Longonjo solar and diesel generation plant.
SRK have been appointed to undertake the detailed design of the TSF and have solicited the services from specialist companies to provide key inputs into the design so as to meet Global Industry Standards on Tailings Management. The detailed design is progressing well and the first construction activities are scheduled to commence in the coming weeks.
As part of the mine construction progress the Project has continued engagements with the local community over the delivery of the Resettlement Action Plan (RAP). The first tranche of project affected households are embarking on their journey towards livelihood restoration with a comprehensive agricultural development plan underway, with training modules geared to not only replace livelihoods but offer further enhancement opportunities including home-based vegetable gardens.
Project delivery is scheduled as per the table below.

Site Construction Progress

Establishment and levelling of the Processing Plant Platform


Community Engagement Meetings


350 person camp installed on site
The early works programme entails construction and development of the civil works for the camp, the rehabilitation of the access road to Longonjo camp and the agricultural demonstration plots under the Livelihood Restoration Programme.
Site Construction Progress


350 person camp installed on site


Bushtec Accommodation Installed


Laundry Facilities Installation


Further Deliveries to Site

Contractors Laydown – Final Layer Backfilling

Grass Planting Preparation – Soil Erosion Prevention

Site Layout

March 2024

April 2024

June 2024



Site Overall Progress Timeline


Camp Kitchen Equipment Transported via the Lobito Port – Arriving and Stored on Site


Ablution & Office Containers Transported by Road From South Africa – Arriving and Stored on Site

Main Road – Storm Water Drains Progress

Storm Water Drains Completed

Kitchen Grease Trap

Water Valve Chambers

Contractors Laydown Area – Earthworks

Camp Electrical Cable Excavated Trenches Bedding Preparations


Practical Training Assessment – Certified Forklift Training Operation

Water Quality Monitoring

Dust Suppression

HSE Daily Meeting

Waste Segregation

Safe Driving Awareness

Emergency Drill Evacuation

Community Engagement Meetings

Community Engagement Meetings

Safe Grinding & Cutting

Forklift Safety Training

Quality Checks

Agriculture Demo Plots

Water Pressure Testing